Render of the Four Square shopfront under its green “Your Local Fresh Grocer” canopy

Four SquareEllerslie

PCI Accelerate

Overview

PCI completed a Four Square supermarket renovation in just 82 hours, work that would traditionally take a three-week programme. Every phase of the build was planned and optimised before work began. Subtrades were briefed on exactly what they needed to deliver and when, keeping work continuous with no downtime. Our site manager coordinated teams and solved problems in real time, our project manager kept the programme aligned and adapted as needed, and our quantity surveyor managed costs to ensure every dollar spent delivered a return. Night shifts added around 10% to the cost but allowed the store to reopen 17 days earlier. That meant the client captured revenue that would otherwise have been lost, including critical weekend trading, when sales volumes are highest. Disruption to the store and its customers was kept to a minimum. Why it matters. This project shows how PCI delivers value beyond construction. A modest investment in accelerated delivery returned far more to the client in trading time, proving that the fastest programme is often the most cost-effective one.

Hours to complete
82
Days ahead of traditional programme
21
% reduction of programme time
50
Days of recovered trading time
17